Amend Stage Order display within a process.

Anyway to amend the visable stage orders within a process. showing either on the To Do List or Watch List.

 

The only solution have been informed of is prefixing the stagename

(Process Name)

     A Stage One

     B Stage three

     C Stage Two

 

Imcurrently using version 7.5 and testing 7.6

 

Employee
Scott
Posts: 150
Registered: 05-11-2010
0 Kudos

Re: Amend Stage Order display within a process.

The only way to do it is by using the prefix you mentioned.  Don't forget that the navigation tree will only show the Stage Names where that user has at least one folder sitting in that stage at that moment, so most likely there will be holes in that list that is presented.

Scott Leclerc
Solutions Architect
Americas BPM PS
Metastorm, Inc.
scott.leclerc@metastorm.com

See. Think. Do. Business to the Power of 3™
www.metastorm.com
Occasional Advisor
DanAdmin
Posts: 17
Registered: 07-26-2010
0 Kudos

Re: Amend Stage Order display within a process.

Hi Scott,

 

Many thanks for your quick response.

 

Cheers

 

Dan

Esteemed Contributor
Jerome҉
Posts: 740
Registered: 05-18-2010
0 Kudos

Re: Amend Stage Order display within a process.

I requested that this be set to the priority order (the order as set in the Designer), a great many years ago. Nobody seemed to know what I was talking about, however....

line spacer line
spacerFollow Metastorm on:
spacer Twitter YouTube Blog iTunes LinkedIn Metastorm Community Central, MC2
spacer Copyright © 2011 OpenText Corporation. All Rights Reserved.spacer About Metastormspacer Privacyspacer Legalspacer Site Mapspacer RSSspacer Contact Us
Microsoft Gold Certified Partner
Powered by Windows Azure
line spacer line